As part of the discussion related to the implementation of investment, production and repair programs, Chairman of the Management Board S.S. Tyutebaev held a meeting at Ekibastuz GRES-1.

Альмира Ауелбаева June 13, 2023

As part of the discussion related to the implementation of investment, production and repair programs, Chairman of the Management Board S.S. Tyutebaev held a meeting at Ekibastuz GRES-1.
 
The current work on the restoration of power unit No. 1 was analyzed, and the progress of its implementation was assessed. Initiative projects aimed at ensuring production in 8-block mode and meeting environmental requirements were discussed. These measures are aimed at optimizing production processes and compliance with high standards of environmental safety. The meeting was also attended by representatives of contracting organizations, heads of structural divisions of the station responsible for the implementation of projects. This allows for coordinated and efficient work between different structures.

Hotline of LLP "Ekibastuz GRES-1 named after Bulat Nurzhanov"